Shear
The shear requirements are no different from a normal slab system, and the ribs themselves do not require shear stirrups.
CORCON is a hybrid multi-ribbed slab and beam system that uses the best properties of a slab, with beams to stiffen it and reduce deflection. This page carries the original technical manual's design notes and its simple design load and span charts, for engineers and specifiers sizing a floor.
The shear requirements are no different from a normal slab system, and the ribs themselves do not require shear stirrups.
CORCON can be applied to any span and loading. Telescopic beam moulds and inserts vary the rib depth from a nominal 50 mm depression up to 300 mm deep for extra-heavy loads or spans over 8–9 m.
By reducing the rib spacing from 1,200 mm and using continuity and post-tensioning, spans can be increased to 14 m.
Small spans of around 3 m can use CORCON with a “flat” insert mould.
Primary beams can be designed as upstand beams where suitable, allowing continuous laying of CORCON ribs.
Rib beams sit 1,200 mm apart, and what a floor can carry comes down to two things working against each other — how deep the beam is, and how far it has to span between supports. A deeper beam, or a shorter span, carries more; stretch the span without adding depth and the capacity falls away. The usual fix isn't to stop there: going deeper, or tensioning steel strand through the beam before it takes any load (post-tensioning), gets a long span back up to a proper working load again.
Single span, 1.5-hour fire rating. Three common beam depths. Representative shape of the tested figures, not a substitute for the full tables.
Figures were prepared to the Australian standards in force at the time — always check them against current standards before use.
This is the main case used through most of this guide, and the rating the system is most commonly specified to: a bay resting on supports at both ends, like a single room, protected for 1.5 hours in a fire. A mid-depth beam over a moderate span comfortably carries a typical office floor — desks, filing cabinets, people moving around. Push that same beam noticeably further and the allowance drops right down, to a fraction of what even a lightly used room needs — which is exactly where a deeper beam or post-tensioning takes back over, recovering a proper office-level load even at the longer span.
Key figures
The same simply-supported arrangement, but built to a lighter, 0.5-hour fire protection instead of 1.5 hours. Less fire protection means less concrete cover is needed, so for a given span the beam can often be shallower than the 1.5-hour tables call for — worth considering wherever a project's fire engineer confirms the lower rating is acceptable.
Key figures
Here the rib carries on over an in-between support instead of stopping and starting at every bay, which is more efficient — it reaches further for the same beam depth, at the cost of a small, predictable amount of extra sag. A 300 mm beam in this arrangement reaches out to a 10.5 m span carrying a light, roof-type load, sagging by only about 1/300th of that length — roughly 35 mm over the full 10.5 m, not something anyone standing in the room would notice. It's the arrangement specifiers reach for on longer runs, such as warehouse floors or car parks.
Key figures
The full span and load tables — every beam depth, bar schedule and exact kPa figure tested — are available to engineers and specifiers sizing an actual floor.